Alderney
Regional Environmental Assessment of Renewable Energy:
Environmental Report
Electromagnetic Field (EMF):
Produce a cable laying plan to minimise EMF at or above the seabed. This will include
consideration of cable design and installation (e.g. bury cables where practicable).
5.3.2.12 Residual impact
The mitigation measures identified in Section 5.3.2.11 could reduce the potential impacts of the
Draft Plan, thereby resulting in a lower level of residual impact. However, it is not possible, with
any level of certainty, to determine the exact level of residual impact at the plan level as the
extent of mitigation achievable will be heavily dependent on project specific factors. The
significance of potential residual impacts has been estimated and are summarised in Table 15.
R/4001/7
80
R.2129